Steelfixing SWMS

Date
Category
Industry
Residential high-rise construction
Location
Inner Brisbane
Deliverables
Audit letter to subcontractor, two replacement SWMS and task-observation field supplement
Reference
WHS Act 2011 (Qld), WHS Regulation 2011 (Qld) ss 291 and 299, Queensland Codes of Practice

Steelfixing SWMS - Case Study 05

Background

Background

On an inner-Brisbane residential high-rise development, the steelfixing subcontractor submitted one safe work method statement (SWMS) for the initial groundworks and footing construction. Twelve months later, a spot audit unexpectedly found that no superstructure SWMS had ever been requested or submitted. Until that discovery, high-risk superstructure steelfixing had continued without SWMS coverage, while the contractor’s document-control system failed to identify the changed work.

Scope

Scope

The spot audit was requested by the contractor after a near miss was recorded with the regulator. OHSE Consultants assessed both the subcontractor’s SWMS content and the contractor’s register for managing high-risk work. Assistance included an audit letter requesting separate substructure and superstructure SWMS. A task-observation supplement and changes to the contractor’s internal systems for requesting, reviewing and updating SWMS when the construction work changed.

Findings

Findings

The subcontractor’s original SWMS covered groundworks and footing construction. High-risk superstructure steelfixing had then proceeded for 12 months without anyone noticing that high-risk work was being completed without a SWMS. The other failure was the contractor’s lack of system control: no process triggered a request, review or update when work moved into the superstructure. This allowed high-risk work to remain undetected and unmanaged. Both the contractor and subcontractor were in breach.

Guidance

Guidance

Immediate action was required to develop separate documents covering substructure activities and high-risk superstructure steelfixing. The contractor also needed to adjust their IMS to link an additional SWMS to the future superstructure construction program. Before future high-risk work commenced or changed, the system had to trigger a request, review and update the relevant SWMS and its controls.

Outcomes

Outcomes

The contractor, subcontractor and auditor acted urgently. The auditor and steelfixing subcontractor developed and implemented separate substructure and superstructure SWMS with controls matched to each work phase. The contractor updated its SWMS system so changes in high-risk work would trigger document requests, review and revision. This corrected the immediate breach and the underlying system failure that had allowed it to continue.

Conclusion

Conclusion

The initial spot audit identified an iternal management system failure that had allowed unlawful, uncontrolled high-risk work to continue for 12 months, leaving both contractor and subcontractor in breach. Rapid action to resubmit the steelfixing SWMS and the immediate repair the contractor’s management system will advert similar errors. Phase-based controls now govern the projects schedule, supported by a process for detecting changes before high-risk activities proceeded without the correct SWMS.

Background

Background

On an inner-Brisbane residential high-rise development, the steelfixing subcontractor submitted one safe work method statement (SWMS) for the initial groundworks and footing construction. Twelve months later, a spot audit unexpectedly found that no superstructure SWMS had ever been requested or submitted. Until that discovery, high-risk superstructure steelfixing had continued without SWMS coverage, while the contractor’s document-control system failed to identify the changed work.

Scope

Scope

The spot audit was requested by the contractor after a near miss was recorded with the regulator. OHSE Consultants assessed both the subcontractor’s SWMS content and the contractor’s register for managing high-risk work. Assistance included an audit letter requesting separate substructure and superstructure SWMS. A task-observation supplement and changes to the contractor’s internal systems for requesting, reviewing and updating SWMS when the construction work changed.

Findings

Findings

The subcontractor’s original SWMS covered groundworks and footing construction. High-risk superstructure steelfixing had then proceeded for 12 months without anyone noticing that high-risk work was being completed without a SWMS. The other failure was the contractor’s lack of system control: no process triggered a request, review or update when work moved into the superstructure. This allowed high-risk work to remain undetected and unmanaged. Both the contractor and subcontractor were in breach.

Guidance

Guidance

Immediate action was required to develop separate documents covering substructure activities and high-risk superstructure steelfixing. The contractor also needed to adjust their IMS to link an additional SWMS to the future superstructure construction program. Before future high-risk work commenced or changed, the system had to trigger a request, review and update the relevant SWMS and its controls.

Outcomes

Outcomes

The contractor, subcontractor and auditor acted urgently. The auditor and steelfixing subcontractor developed and implemented separate substructure and superstructure SWMS with controls matched to each work phase. The contractor updated its SWMS system so changes in high-risk work would trigger document requests, review and revision. This corrected the immediate breach and the underlying system failure that had allowed it to continue.

Conclusion

Conclusion

The initial spot audit identified an iternal management system failure that had allowed unlawful, uncontrolled high-risk work to continue for 12 months, leaving both contractor and subcontractor in breach. Rapid action to resubmit the steelfixing SWMS and the immediate repair the contractor’s management system will advert similar errors. Phase-based controls now govern the projects schedule, supported by a process for detecting changes before high-risk activities proceeded without the correct SWMS.

Documents audited and replaced

Document Scope Status
Original subcontractor SWMS Substructure works only; at-height steelfixing not covered Rejected
Groundworks SWMS, rev 2.0 Resubmitted: Ground-level steelfixing, revised Issued
Superstructure SWMS, rev 1.0 Resubmitted: At-height steelfixing, revised Issued

"A spot audit exposed 12 months of unlawful high-risk steelfixing and a contractor system failure that left both contractor and subcontractor in breach, triggering urgent correction of both SWMS and system controls."